R.C. Thomas Hydroelectric Project

24 MW ETEC hydroelectric facility on the Trinity River near Livingston, TX

  • Estimated Commercial Operation: Q3 of 2018

  • Received FERC license in 3Q 2012

  • Turbine contract awarded in 2Q 2010

  • Executed EPC contract, approved August 2013

  • CREB – Received $10.2 million in 2008, $25 million in 2009 and $15 million in 2011

  • Remainder to be funded by RUS.